Scope

Guides showing step by step sequences on how to install main inlet valves for hydroelectrical units on site. Each step will be defined with an Objective of the work, Explanation of the work and recommendations such as measurements to take and tolerances to follow

Purpose

There are many hydroelectric power plants that uses Main inlet valve to control the flow of water into the hydroelectrical unit. Our experience show that there are no existing guide to cover the installation and/or replacement of the main inlet valves.

Comment on proposal

Required form fields are indicated by an asterisk (*) character.


Please email further comments to: admin.start@bsigroup.com

Follow standard

You are now following this standard. Weekly digest emails will be sent to update you on the following activities:

You can manage your follow preferences from your Account. Please check your mailbox junk folder if you don't receive the weekly email.

Unfollow standard

You have successfully unsubscribed from weekly updates for this standard.

Error